The Karnataka based steel major is currently expanding its production capacity at the Hospet site by two million tons per year. At the new electrical steel works, Siemens is projecting and delivering the mechanical and electrical equipment for a new electric arc furnace with a tapping weight of 110 tonnes, a 110-tonne ladle furnace, a vacuum degassing plant and the alloying and additive systems. The electric arc furnace is specially designed for the combined charging of direct-reduced iron (DRI) and hot metal. The electric arc furnace, the ladle furnace, the material charging systems and other auxiliaries are being equipped with a dedusting system. The scope of supply also includes the entire Level 1 automation and process automation (Level 2) systems, furnace transformers and a dynamic compensation system Static Var Compensator (SVC).
Siemens received the order from BMM Ispat at the beginning of 2012, as part of their integrated steel plant project, a flexible bar mill in Hospet with an annual capacity of 850,000 tonnes. By the end of 2013, the mill will roll reinforcing steel, round bars, flat and square bars, angles and sections. The crude steel for these products will be produced in the new electrical steel works.